City of Markham Construction Notice

November 2, 2026

Topic:  Pomona Creek Park – request for permission to enter for work on YNSE

Start Date: December 1, 2026
End Date: January 31, 2027

What is happening?

North End Connectors Construction (the “Contractor”), a contractor for Metrolinx, is doing work on the Pomona Creek Pedestrian Bridge as part of Yonge North Subway Extension Project (the “Project”) to install equipment and take readings of Ground Monitoring Points (“GMP”), Building Monitoring Points (“BMP”), Multi Point Borehole Extensometers (“MPBX”), Utility Monitoring Points (“UMP”), (collectively, the “Instruments”). Further details are shown in the notices below.

The Contractor plans to be on site between December 1, 2026, to January 31, 2027, for the installation of the Instruments. Access for readings of the Instruments will be from February 1, 2027, to September 30, 2027.

Please see construction notices here:

Construction Notice No. 1 – GIMP – Royal Orchard Park

Construction Notice No. 2 – GIMP – Pomona Creek Pedestrian Bridge